Bwacha constituency

9 CDF projects tracked in Bwacha, Central: budgets, status, contractors and sources.

Central Province · 9 published CDF projects tracked across all published years · K17.8m in published budgets (9 of 9 projects publish amounts). Funding year is published for 9 of 9.

Approved: 9

Record: based on published project lists.

The audited record

The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.

Financial year 2024

ComponentTotal funds availableSpentUnspentUnspent / spent
Community ProjectsK17,825,525K9,899,159K7,926,36744% unspent · 56% spent
Empowerment GrantK2,444,873K2,444,873K00% unspent · 100% spent
Secondary Boarding and Skills Development - BursariesK8,877,542K5,105,922K3,771,62042% unspent · 58% spent
LoansK6,784,821K6,201,788K583,0339% unspent · 91% spent
Administrative CostK1,798,081K1,798,081K00% unspent · 100% spent

Community Projects

Total funds availableK17,825,525
SpentK9,899,159
UnspentK7,926,367
Unspent / spent44% unspent · 56% spent

balance brought forward K6,513,669 · 2024 funding K11,311,856

Empowerment Grant

Total funds availableK2,444,873
SpentK2,444,873
UnspentK0
Unspent / spent0% unspent · 100% spent

balance brought forward K796,671 · 2024 funding K1,648,202

Secondary Boarding and Skills Development - Bursaries

Total funds availableK8,877,542
SpentK5,105,922
UnspentK3,771,620
Unspent / spent42% unspent · 58% spent

balance brought forward K4,757,036 · 2024 funding K4,120,506

Loans

Total funds availableK6,784,821
SpentK6,201,788
UnspentK583,033
Unspent / spent9% unspent · 91% spent

balance brought forward K2,552,996 · 2024 funding K3,521,964 · loan repayments received K651,600 · interest accrued K58,261

Administrative Cost

Total funds availableK1,798,081
SpentK1,798,081
UnspentK0
Unspent / spent0% unspent · 100% spent

balance brought forward K713,737 · 2024 funding K1,084,344

Community Projects: balance brought forward K6,513,669 · 2024 funding K11,311,856

Empowerment Grant: balance brought forward K796,671 · 2024 funding K1,648,202

Secondary Boarding and Skills Development - Bursaries: balance brought forward K4,757,036 · 2024 funding K4,120,506

Loans: balance brought forward K2,552,996 · 2024 funding K3,521,964 · loan repayments received K651,600 · interest accrued K58,261

Administrative Cost: balance brought forward K713,737 · 2024 funding K1,084,344

2023 cohort — brought forward: 4 projects

Implemented — 1 (25%)In progress — 0 (0%)Not implemented — 3 (75%)

2024 cohort — approved: 17 projects

Implemented — 12 (71%)In progress — 3 (18%)Not implemented — 2 (12%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)

Financial year 2023

ComponentAmount receivedSpentUnspentUnspent / spent
Community ProjectsK15,216,294K8,534,383K6,681,91144% unspent · 56% spent
Empowerment GrantsK2,151,857K2,143,065K8,7920% unspent · 100% spent
Soft LoansNot published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - BursariesK9,209,407K4,452,241K4,757,16652% unspent · 48% spent
Administrative CostsK1,415,695K1,550,869-K135,174-10% unspent · 110% spent

Community Projects

Amount receivedK15,216,294
SpentK8,534,383
UnspentK6,681,911
Unspent / spent44% unspent · 56% spent

Empowerment Grants

Amount receivedK2,151,857
SpentK2,143,065
UnspentK8,792
Unspent / spent0% unspent · 100% spent

Soft Loans

Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.

Secondary Boarding and Skills Development - Bursaries

Amount receivedK9,209,407
SpentK4,452,241
UnspentK4,757,166
Unspent / spent52% unspent · 48% spent

Administrative Costs

Amount receivedK1,415,695
SpentK1,550,869
Unspent-K135,174
Unspent / spent-10% unspent · 110% spent

2022 cohort — brought forward: 12 projects

Implemented — 12 (100%)In progress — 0 (0%)Not implemented — 0 (0%)

2023 cohort — approved: 10 projects

Implemented — 1 (10%)In progress — 1 (10%)Not implemented — 8 (80%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)