Kankoyo constituency

2 CDF projects tracked in Kankoyo, Copperbelt: budgets, status, contractors and sources.

Copperbelt Province · 2 published CDF projects tracked across all published years · per-project amounts not published in published budgets (0 of 2 projects publish amounts).

Approved: 2

Record: based on tender notices.

The audited record

The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.

Financial year 2024

ComponentTotal funds availableSpentUnspentUnspent / spent
Community ProjectsK22,627,680K20,945,956K1,681,7247% unspent · 93% spent
Empowerment GrantK4,214,308K2,350,200K1,864,10844% unspent · 56% spent
Secondary Boarding and Skills Development - BursariesK6,002,668K4,392,418K1,610,25027% unspent · 73% spent
LoansK7,097,299K6,530,625K566,6748% unspent · 92% spent
Administrative CostK2,190,340K1,621,983K568,35726% unspent · 74% spent

Community Projects

Total funds availableK22,627,680
SpentK20,945,956
UnspentK1,681,724
Unspent / spent7% unspent · 93% spent

balance brought forward K9,488,207 · 2024 funding K13,139,473

Empowerment Grant

Total funds availableK4,214,308
SpentK2,350,200
UnspentK1,864,108
Unspent / spent44% unspent · 56% spent

balance brought forward K2,130,000 · 2024 funding K2,084,308

Secondary Boarding and Skills Development - Bursaries

Total funds availableK6,002,668
SpentK4,392,418
UnspentK1,610,250
Unspent / spent27% unspent · 73% spent

balance brought forward K3,419,863 · 2024 funding K2,582,805

Loans

Total funds availableK7,097,299
SpentK6,530,625
UnspentK566,674
Unspent / spent8% unspent · 92% spent

balance brought forward K3,720,506 · 2024 funding K3,036,492 · loan repayments received K181,959 · interest accrued K158,342

Administrative Cost

Total funds availableK2,190,340
SpentK1,621,983
UnspentK568,357
Unspent / spent26% unspent · 74% spent

balance brought forward K1,093,336 · 2024 funding K1,097,004

Community Projects: balance brought forward K9,488,207 · 2024 funding K13,139,473

Empowerment Grant: balance brought forward K2,130,000 · 2024 funding K2,084,308

Secondary Boarding and Skills Development - Bursaries: balance brought forward K3,419,863 · 2024 funding K2,582,805

Loans: balance brought forward K3,720,506 · 2024 funding K3,036,492 · loan repayments received K181,959 · interest accrued K158,342

Administrative Cost: balance brought forward K1,093,336 · 2024 funding K1,097,004

2023 cohort — brought forward: 23 projects

Implemented — 23 (100%)In progress — 0 (0%)Not implemented — 0 (0%)

2024 cohort — approved: 31 projects

Implemented — 29 (94%)In progress — 1 (3%)Not implemented — 1 (3%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)

Financial year 2023

ComponentAmount receivedSpentUnspentUnspent / spent
Community ProjectsK15,216,297K5,401,267K9,815,03065% unspent · 35% spent
Empowerment GrantsK2,151,857K2,143,065K8,7920% unspent · 100% spent
Soft LoansNot published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - BursariesK5,379,641K5,653,250-K273,609-5% unspent · 105% spent
Administrative CostsK1,415,695K1,654,179-K238,484-17% unspent · 117% spent

Community Projects

Amount receivedK15,216,297
SpentK5,401,267
UnspentK9,815,030
Unspent / spent65% unspent · 35% spent

Empowerment Grants

Amount receivedK2,151,857
SpentK2,143,065
UnspentK8,792
Unspent / spent0% unspent · 100% spent

Soft Loans

Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.

Secondary Boarding and Skills Development - Bursaries

Amount receivedK5,379,641
SpentK5,653,250
Unspent-K273,609
Unspent / spent-5% unspent · 105% spent

Administrative Costs

Amount receivedK1,415,695
SpentK1,654,179
Unspent-K238,484
Unspent / spent-17% unspent · 117% spent

2022 cohort — brought forward: 16 projects

Implemented — 14 (88%)In progress — 2 (12%)Not implemented — 0 (0%)

2023 cohort — approved: 50 projects

Implemented — 27 (54%)In progress — 0 (0%)Not implemented — 23 (46%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)