Southern Province · 40 published CDF projects tracked across all published years · K24m in published budgets (32 of 40 projects publish amounts). Funding year is published for 1 of 40.
Approved: 6 · Completed: 20 · In progress: 1 · Ongoing: 11 · Stalled: 2
Record: based on council and news reports.
2023 CDF — 1 projects
Funding year not published — 39 projects
Completion of Construction of a 1x3 Classroom Block at Kanchele Primary School
Kanchele · education
K185,432 · Completed
Completion of a 1x3 Classroom Block at Kabuyu Secondary School
Simango · education
K85,905 · Completed
Completion of a Science Laboratory at Kauwe Secondary School
Kauwe · education
K550,000 · Ongoing
Construction of Chief's Palace
Nyawa · administration
Not published · Approved
Construction of Culverts at Nsongwe Stream
Mukuni · roads
K566,350 · Completed
Construction of Secondary School in Moomba Central - Lot 1 (Two 1x3 Classroom Blocks)
Moomba · education
K1,958,403 · Ongoing
Construction of Secondary School in Moomba Central - Lot 2 (Four Staff Houses)
Moomba · education
K1,891,929 · Ongoing
Construction of Secondary School in Moomba Central - Lot 3 (One 1x2 Classroom Block and Ablution Blocks)
Moomba · education
K1,285,310 · Ongoing
Construction of Secondary School in Moomba Central - Lot 4 (Water Reticulation)
Moomba · water
Not published · Approved
Construction of Two Dormitories and Two Ablution Blocks at Nyawa Secondary School
Nyawa · education
K2,666,658 · Ongoing
Construction of Two Double VIP Latrines at Saala Primary School
Kazungula Central · sanitation
K154,790 · Ongoing
Construction of a 1x2 Classroom Block at Chibuyu Primary School and Procurement of 80 Additional Desks
Katapazi · education
K624,058 · Completed
Construction of a 1x2 Classroom Block at Katombora Secondary School
Mandia · education
K421,982 · Completed
Construction of a 1x3 Classroom Block at Chileya Village
Ngwezi · education
K624,992 · Completed
Construction of a 1x3 Classroom Block at Kalamba Primary School
Moomba · education
K772,985 · Completed
Construction of a 1x3 Classroom Block at Mulele Community School
Sikaunzwe · education
K688,208 · Completed
Construction of a 1x3 Classroom Block at Sekute Primary School
Sekute · education
K577,231 · Completed
Construction of a 1x3 Classroom Block at Vaala Primary School
Bombwe · education
K638,325 · Completed
Construction of a Collapsed Septic Tank at Makunka Primary School
Sekute · sanitation
K50,000 · Completed
Construction of a Computer Science Laboratory at Kazungula Boarding School
Kazungula Central · education
K631,651 · Stalled
Construction of a Maternity Annex at Chinkonzya Rural Health Centre
Simango · health
K745,889 · Ongoing
Construction of a Maternity Annex at Kazungula Central Clinic
Kazungula Central · health
K728,943 · Ongoing
Construction of a Maternity Annex at Lunungu Rural Health Centre
Ngwezi · health
K927,312 · Stalled
Construction of a Maternity Wing at Busanga Health Facility
Nyawa · health
K749,198 · Ongoing
Construction of a Maternity Wing at Katondo Clinic
Kauwe · health
Not published · Approved
Construction of a Staff House at Kanimbwa Community School
Nyawa · education
K200,579 · Ongoing
Desks for Different Schools
All · education
K700,000 · Completed
Electrification of Musokotwane Clinic
Musokotwane · health
Not published · Approved
Procurement of CDF Monitoring Vehicle
equipment
K1,200,000 · Completed
Procurement of Desks for Kanono Primary School
Kanchele · education
K69,720 · Completed
Purchase and Supply of Medical Equipment for Six Maternity Annexes
All · equipment
Not published · Approved
Purchase of a Police Vehicle
All · equipment
Not published · Completed
Rehabilitation of Piped Water Supply System in Mukuni Central
Mukuni · water
K237,350 · Completed
Roof Rehabilitation at Katapazi Primary School
education
Not published · In progress
Roofing of Two 1x2 Classroom Blocks at Simumbwe Primary School
Kauwe · education
K137,600 · Completed
Roofing of a 1x1 Classroom Block at Riverview School
Kazungula Central · education
K55,970 · Completed
Roofing of a Blown-Off 1x2 Classroom Block Roof at Chunga Namalazo Primary School
Mukuni · education
K124,994 · Completed
Rural Electrification
All · infrastructure
Not published · Approved
Solar Batteries for Lupani Primary School
equipment
K100,000 · Completed
The audited record
The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.
Financial year 2024
| Component | Total funds available | Spent | Unspent | Unspent / spent |
|---|---|---|---|---|
| Community Projects | K26,356,197 | K21,184,706 | K5,171,491 | 20% unspent · 80% spent |
| Empowerment Grant | K444,126 | K1,196,105 | -K751,979 | -169% unspent · 269% spent |
| Secondary Boarding and Skills Development - Bursaries | K4,370,785 | K5,351,569 | -K980,784 | -22% unspent · 122% spent |
| Loans | K3,214,246 | K2,515,260 | K698,986 | 22% unspent · 78% spent |
| Administrative Cost | K1,660,147 | K2,227,012 | -K566,865 | -34% unspent · 134% spent |
Community Projects
balance brought forward K21,530,633 · 2024 funding K4,825,564
Empowerment Grant
balance brought forward K140,126 · 2024 funding K304,000
Secondary Boarding and Skills Development - Bursaries
balance brought forward K2,850,785 · 2024 funding K1,520,000
Loans
balance brought forward K759,051 · 2024 funding K950,436 · loan repayments received K957,214 · interest accrued K547,545
Administrative Cost
balance brought forward K1,260,147 · 2024 funding K400,000
Community Projects: balance brought forward K21,530,633 · 2024 funding K4,825,564
Empowerment Grant: balance brought forward K140,126 · 2024 funding K304,000
Secondary Boarding and Skills Development - Bursaries: balance brought forward K2,850,785 · 2024 funding K1,520,000
Loans: balance brought forward K759,051 · 2024 funding K950,436 · loan repayments received K957,214 · interest accrued K547,545
Administrative Cost: balance brought forward K1,260,147 · 2024 funding K400,000
2023 cohort — brought forward: 16 projects
2024 cohort — approved: 19 projects
Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)
Financial year 2023
| Component | Amount received | Spent | Unspent | Unspent / spent |
|---|---|---|---|---|
| Community Projects | K14,279,546 | K9,997,331 | K4,282,215 | 30% unspent · 70% spent |
| Empowerment Grants | K2,151,857 | K2,077,352 | K74,505 | 3% unspent · 97% spent |
| Soft Loans | Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table. | |||
| Secondary Boarding and Skills Development - Bursaries | K5,379,641 | K3,712,342 | K1,667,299 | 31% unspent · 69% spent |
| Administrative Costs | K1,415,695 | K868,568 | K547,127 | 39% unspent · 61% spent |
Community Projects
Empowerment Grants
Soft Loans
Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - Bursaries
Administrative Costs
2022 cohort — brought forward: 15 projects
2023 cohort — approved: 14 projects
Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)