Luapula Province · 27 published CDF projects tracked across all published years · per-project amounts not published in published budgets (0 of 27 projects publish amounts). Funding year is published for 27 of 27.
Completed: 22 · Ongoing: 5
Record: based on published project lists. No approval list has been published for this constituency — the public record here starts at handover.
2025 CDF — 11 projects
Construction and Equipping of Mutima Science Laboratory
Munwa · education
Not published · Completed
Construction of Michelo Water Scheme
Michelo · water
Not published · Completed
Construction of Sepe Rural Health Post Ablution Block
Michelo · sanitation
Not published · Completed
Construction of Sepe Rural Health Post Staff Houses (2)
Michelo · health
Not published · Completed
Construction of Staff Houses at Chebele RHP
Kalanga · health
Not published · Ongoing
Construction of a 10,000 Litre Water Scheme at Chula Village
Musonda · water
Not published · Ongoing
Construction of a 1x3 CRB at Mutima Primary School
Munwa · education
Not published · Ongoing
Construction of a Mortuary at Katuta RHP
Mpasa · health
Not published · Completed
Construction of a Water Scheme at Chula Village
Musonda · water
Not published · Ongoing
Construction of an Ablution Block and Upgrading of a Borehole at Kabila Primary School
Musonda · sanitation
Not published · Ongoing
Rehabilitation of Mutima 1x2 CRB
Munwa · education
Not published · Completed
2024 CDF — 3 projects
Construction of a Drainage System from Shichama to Checkpoint
Kalanga · infrastructure
Not published · Completed
Construction of a Staff House at Michelo Primary School
Michelo · education
Not published · Completed
Rehabilitation of Mwendago Crossing Point
Mwendango · infrastructure
Not published · Completed
2022 CDF — 13 projects
Completion of Kanyemba Health Post
Kalanga · health
Not published · Completed
Completion of a 1x2 at Chibumbu Primary
Lundashi · education
Not published · Completed
Completion of a 1x3 at Musonda Secondary School
Musonda · education
Not published · Completed
Construction 1x3 CRB at Kashiba Secondary School
Nsomfi · education
Not published · Completed
Construction of a 1x3 CRB at Katuta
Mpasa · education
Not published · Completed
Construction of a 1x3 CRB at Shichama Primary School
Kalanga · education
Not published · Completed
Construction of a 1x3 at Chibondo Secondary School
Mpasa · education
Not published · Completed
Construction of a RHP at Chebele
Kalanga · health
Not published · Completed
Construction of a Water Scheme at Chebele RHP
Kalanga · water
Not published · Completed
Construction of a Water Scheme at Mweshi and Nkomba
Kalanga · water
Not published · Completed
Construction of a Water Scheme in Musonda
Musonda · water
Not published · Completed
Construction of an Embankment at Katuta
Mpasa · infrastructure
Not published · Completed
Rehabilitation of a 1x2 at Tangwa
Mpasa · education
Not published · Completed
The audited record
The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.
Financial year 2024
| Component | Total funds available | Spent | Unspent | Unspent / spent |
|---|---|---|---|---|
| Community Projects | K24,094,944 | K20,640,733 | K3,454,211 | 14% unspent · 86% spent |
| Empowerment Grant | K2,390,920 | K2,385,000 | K5,920 | 0% unspent · 100% spent |
| Secondary Boarding and Skills Development - Bursaries | K6,230,860 | K3,219,222 | K3,011,638 | 48% unspent · 52% spent |
| Loans | K6,239,447 | K4,566,003 | K1,673,444 | 27% unspent · 73% spent |
| Administrative Cost | K2,850,878 | K1,853,800 | K997,078 | 35% unspent · 65% spent |
Community Projects
balance brought forward K18,770,344 · 2024 funding K5,324,600 · other receipts K0
Empowerment Grant
balance brought forward K62,611 · 2024 funding K2,328,309
Secondary Boarding and Skills Development - Bursaries
balance brought forward K6,230,860 · 2024 funding K0
Loans
balance brought forward K2,619,932 · 2024 funding K2,938,644 · other receipts K0 · loan repayments received K565,048 · interest accrued K115,823
Administrative Cost
balance brought forward K1,251,649 · 2024 funding K1,599,229 · other receipts K0
Community Projects: balance brought forward K18,770,344 · 2024 funding K5,324,600 · other receipts K0
Empowerment Grant: balance brought forward K62,611 · 2024 funding K2,328,309
Secondary Boarding and Skills Development - Bursaries: balance brought forward K6,230,860 · 2024 funding K0
Loans: balance brought forward K2,619,932 · 2024 funding K2,938,644 · other receipts K0 · loan repayments received K565,048 · interest accrued K115,823
Administrative Cost: balance brought forward K1,251,649 · 2024 funding K1,599,229 · other receipts K0
2023 cohort — brought forward: 3 projects
2024 cohort — approved: 12 projects
Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)
Financial year 2023
| Component | Amount received | Spent | Unspent | Unspent / spent |
|---|---|---|---|---|
| Community Projects | K14,082,284 | K2,153,972 | K11,928,312 | 85% unspent · 15% spent |
| Empowerment Grants | K2,082,140 | K2,264,742 | -K182,602 | -9% unspent · 109% spent |
| Soft Loans | Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table. | |||
| Secondary Boarding and Skills Development - Bursaries† | Not published | Not published | Not published | Not published |
| Administrative Costs | K1,363,250 | K1,251,550 | K111,700 | 8% unspent · 92% spent |
Community Projects
Empowerment Grants
Soft Loans
Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - Bursaries†
Administrative Costs
† The report prints this constituency inside a district-combined figure; the split by constituency is not published.
2022 cohort — brought forward: 25 projects
2023 cohort — approved: 5 projects
Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)