Mbala constituency

10 CDF projects tracked in Mbala, Northern: budgets, status, contractors and sources.

Northern Province · 10 published CDF projects tracked across all published years · K22m in published budgets (6 of 10 projects publish amounts). Funding year is published for 5 of 10.

Completed: 7 · Ongoing: 3

Record: based on council newsletters. No approval list has been published for this constituency — the public record here starts at handover.

2026 CDF — 1 projects

2025 CDF — 1 projects

2024 CDF — 1 projects

2023 CDF — 1 projects

2022 CDF — 1 projects

Funding year not published — 5 projects

The audited record

The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.

Financial year 2024

ComponentTotal funds availableSpentUnspentUnspent / spent
Community ProjectsK22,033,781K21,716,943K316,8381% unspent · 99% spent
Empowerment GrantK988,000K2,331,000-K1,343,000-136% unspent · 236% spent
Secondary Boarding and Skills Development - BursariesK8,370,617K3,065,612K5,305,00663% unspent · 37% spent
LoansK5,212,178K4,685,385K526,79310% unspent · 90% spent
Administrative CostK1,222,839K7,751,170-K6,528,331-534% unspent · 634% spent

Community Projects

Total funds availableK22,033,781
SpentK21,716,943
UnspentK316,838
Unspent / spent1% unspent · 99% spent

balance brought forward K13,923,782 · 2024 funding K8,109,999

Empowerment Grant

Total funds availableK988,000
SpentK2,331,000
Unspent-K1,343,000
Unspent / spent-136% unspent · 236% spent

balance brought forward K0 · 2024 funding K988,000

Secondary Boarding and Skills Development - Bursaries

Total funds availableK8,370,617
SpentK3,065,612
UnspentK5,305,006
Unspent / spent63% unspent · 37% spent

balance brought forward K8,120,117 · 2024 funding K250,500

Loans

Total funds availableK5,212,178
SpentK4,685,385
UnspentK526,793
Unspent / spent10% unspent · 90% spent

balance brought forward K1,344,917 · 2024 funding K3,001,501 · loan repayments received K835,035 · interest accrued K30,725

Administrative Cost

Total funds availableK1,222,839
SpentK7,751,170
Unspent-K6,528,331
Unspent / spent-534% unspent · 634% spent

balance brought forward K572,839 · 2024 funding K650,000

Community Projects: balance brought forward K13,923,782 · 2024 funding K8,109,999

Empowerment Grant: balance brought forward K0 · 2024 funding K988,000

Secondary Boarding and Skills Development - Bursaries: balance brought forward K8,120,117 · 2024 funding K250,500

Loans: balance brought forward K1,344,917 · 2024 funding K3,001,501 · loan repayments received K835,035 · interest accrued K30,725

Administrative Cost: balance brought forward K572,839 · 2024 funding K650,000

2023 cohort — brought forward: 15 projects

Implemented — 12 (80%)In progress — 2 (13%)Not implemented — 1 (7%)

2024 cohort — approved: 14 projects

Implemented — 6 (43%)In progress — 3 (21%)Not implemented — 5 (36%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)

Financial year 2023

ComponentAmount receivedSpentUnspentUnspent / spent
Community ProjectsK15,269,337K800,124K14,469,21395% unspent · 5% spent
Empowerment GrantsK2,143,065K2,121,857K21,2081% unspent · 99% spent
Soft LoansNot published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - BursariesK5,357,662K2,359,843K2,997,81956% unspent · 44% spent
Administrative CostsK1,409,911K1,268,923K140,98810% unspent · 90% spent

Community Projects

Amount receivedK15,269,337
SpentK800,124
UnspentK14,469,213
Unspent / spent95% unspent · 5% spent

Empowerment Grants

Amount receivedK2,143,065
SpentK2,121,857
UnspentK21,208
Unspent / spent1% unspent · 99% spent

Soft Loans

Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.

Secondary Boarding and Skills Development - Bursaries

Amount receivedK5,357,662
SpentK2,359,843
UnspentK2,997,819
Unspent / spent56% unspent · 44% spent

Administrative Costs

Amount receivedK1,409,911
SpentK1,268,923
UnspentK140,988
Unspent / spent10% unspent · 90% spent

2022 cohort — brought forward: 33 projects

Implemented — 28 (85%)In progress — 4 (12%)Not implemented — 1 (3%)

2023 cohort — approved: 22 projects

Implemented — 1 (5%)In progress — 2 (9%)Not implemented — 19 (86%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)