Zambia CDF Tracker

Nalolo constituency

34 CDF projects tracked in Nalolo, Western: budgets, status, contractors and sources.

Western Province · 34 published CDF projects tracked across all published years · K16.1m in published budgets (34 of 34 projects publish amounts).

Approved: 34

Record: based on approval lists.

Additional funding for the construction of a Chiefs Palace

Muoyo · administration

K157,700 · Approved

Completion of 1x2 classroom block at Sinungu School

Lyamakumba · education

K89,566 · Approved

Construction of 1x3 classroom block at Imafuwa School

Lyamakumba · education

K831,150 · Approved

Construction of 1x3 classroom block at Kataba Primary School

Kataba · education

K821,150 · Approved

Construction of 1x3 classroom block at Likulwe Primary School

Likulwe · education

K831,150 · Approved

Construction of 1x3 classroom block at Lunga School

Muoyo · education

K821,150 · Approved

Construction of 1x3 classroom block at Lwambi School

Mukukutu · education

K821,150 · Approved

Construction of 1x3 classroom block at Mwananyanda Primary School

Kambai · education

K831,150 · Approved

Construction of 1x3 classroom block at Sinungu School

Lyamakumba · education

K796,984 · Approved

Construction of a flushable toilet at Kaanda Primary School

Silowana · sanitation

K300,147 · Approved

Construction of a flushable toilet at Lyande Health Post

Shekela · sanitation

K300,147 · Approved

Construction of a flushable toilet at Makwibi Primary School

Muoyo · sanitation

K300,147 · Approved

Construction of a flushable toilet at Mande Community School

Muoyo · sanitation

K300,147 · Approved

Construction of a flushable toilet at Matongo Primary School

Nanjucha · sanitation

K300,147 · Approved

Construction of a flushable toilet at Nanjucha Primary School

Nanjucha · sanitation

K300,147 · Approved

Construction of a flushable toilet at Nyanye Community School

Shekela · sanitation

K300,274 · Approved

Construction of a flushable toilet at Shekela Primary School

Shekela · sanitation

K300,274 · Approved

Construction of a flushable toilet at Sinungu School

Lyamakumba · sanitation

K300,274 · Approved

Construction of a flushable toilet at Sipungu Primary School

Shekela · sanitation

K300,147 · Approved

Construction of a staff house at Nalolo Royal Health Clinic

Ukolo · health

K427,785 · Approved

Installation of solar powered water reticulation system at Kaanda Primary School

Silowana · water

K112,250 · Approved

Installation of solar powered water reticulation system at Lunga Combined School

Muoyo · water

K194,250 · Approved

Installation of solar powered water reticulation system at Lyande

Shekela · water

K192,250 · Approved

Installation of solar powered water reticulation system at Mande Community School

Muoyo · water

K194,250 · Approved

Installation of solar powered water reticulation system at Matongo Primary School

Nanjucha · water

K194,250 · Approved

Installation of solar powered water reticulation system at Nyanye Community School

Shekela · water

K194,250 · Approved

Installation of solar powered water reticulation system at Shekela Primary School

Shekela · water

K194,250 · Approved

Installation of solar powered water reticulation system at Sinungu Health Post

Lyamakumba · water

K194,250 · Approved

Installation of solar powered water reticulation system at Sinungu School

Lyamakumba · water

K192,250 · Approved

Installation of solar powered water reticulation system at Sipungu Primary School

Shekela · water

K194,250 · Approved

Phase 1 construction of a maternity wing at Litoya Rural Health Clinic

Lubosi · health

K450,000 · Approved

Procurement of 1,886 double desks

All Wards · education

K2,384,146 · Approved

Procurement of a police vehicle

All Wards · equipment

K1,000,000 · Approved

Procurement of an ambulance

All Wards · equipment

K1,000,000 · Approved

The audited record

The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.

Financial year 2024

ComponentTotal funds availableSpentUnspentUnspent / spent
Community ProjectsK16,177,003K16,217,210-K40,2070% unspent · 100% spent
Empowerment GrantK2,347,400K2,347,400K00% unspent · 100% spent
Secondary Boarding and Skills Development - BursariesK2,581,123K2,538,123K43,0002% unspent · 98% spent
LoansK3,718,794K3,619,000K99,7943% unspent · 97% spent
Administrative CostK2,548,586K2,548,586K00% unspent · 100% spent

Community Projects

Total funds availableK16,177,003
SpentK16,217,210
Unspent-K40,207
Unspent / spent0% unspent · 100% spent

balance brought forward K11,822,967 · 2024 funding K4,354,036

Empowerment Grant

Total funds availableK2,347,400
SpentK2,347,400
UnspentK0
Unspent / spent0% unspent · 100% spent

balance brought forward K2,347,400 · 2024 funding K0

Secondary Boarding and Skills Development - Bursaries

Total funds availableK2,581,123
SpentK2,538,123
UnspentK43,000
Unspent / spent2% unspent · 98% spent

balance brought forward K2,581,123 · 2024 funding K0

Loans

Total funds availableK3,718,794
SpentK3,619,000
UnspentK99,794
Unspent / spent3% unspent · 97% spent

balance brought forward K6,178 · 2024 funding K3,445,664 · loan repayments received K212,354 · interest accrued K54,598

Administrative Cost

Total funds availableK2,548,586
SpentK2,548,586
UnspentK0
Unspent / spent0% unspent · 100% spent

balance brought forward K1,016,804 · 2024 funding K1,531,782

Community Projects: balance brought forward K11,822,967 · 2024 funding K4,354,036

Empowerment Grant: balance brought forward K2,347,400 · 2024 funding K0

Secondary Boarding and Skills Development - Bursaries: balance brought forward K2,581,123 · 2024 funding K0

Loans: balance brought forward K6,178 · 2024 funding K3,445,664 · loan repayments received K212,354 · interest accrued K54,598

Administrative Cost: balance brought forward K1,016,804 · 2024 funding K1,531,782

2023 cohort — brought forward: 8 projects

Implemented — 7 (88%)In progress — 0 (0%)Not implemented — 1 (12%)

2024 cohort — approved: 29 projects

Implemented — 2 (7%)In progress — 21 (72%)Not implemented — 6 (21%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)

Financial year 2023

ComponentAmount receivedSpentUnspentUnspent / spent
Community ProjectsK14,261,546K6,418,397K7,843,14955% unspent · 45% spent
Empowerment GrantsK2,151,857K2,118,200K33,6572% unspent · 98% spent
Soft LoansNot published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - BursariesK5,179,679K3,469,938K1,709,74133% unspent · 67% spent
Administrative CostsK1,415,695K1,415,695K00% unspent · 100% spent

Community Projects

Amount receivedK14,261,546
SpentK6,418,397
UnspentK7,843,149
Unspent / spent55% unspent · 45% spent

Empowerment Grants

Amount receivedK2,151,857
SpentK2,118,200
UnspentK33,657
Unspent / spent2% unspent · 98% spent

Soft Loans

Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.

Secondary Boarding and Skills Development - Bursaries

Amount receivedK5,179,679
SpentK3,469,938
UnspentK1,709,741
Unspent / spent33% unspent · 67% spent

Administrative Costs

Amount receivedK1,415,695
SpentK1,415,695
UnspentK0
Unspent / spent0% unspent · 100% spent

2022 cohort — brought forward: 21 projects

Implemented — 15 (71%)In progress — 6 (29%)Not implemented — 0 (0%)

2023 cohort — approved: 33 projects

Implemented — 30 (91%)In progress — 2 (6%)Not implemented — 1 (3%)

Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)

?How to read
this tracker