Western Province · 34 published CDF projects tracked across all published years · K16.1m in published budgets (34 of 34 projects publish amounts).
Approved: 34
Record: based on approval lists.
Additional funding for the construction of a Chiefs Palace
Muoyo · administration
K157,700 · Approved
Completion of 1x2 classroom block at Sinungu School
Lyamakumba · education
K89,566 · Approved
Construction of 1x3 classroom block at Imafuwa School
Lyamakumba · education
K831,150 · Approved
Construction of 1x3 classroom block at Kataba Primary School
Kataba · education
K821,150 · Approved
Construction of 1x3 classroom block at Likulwe Primary School
Likulwe · education
K831,150 · Approved
Construction of 1x3 classroom block at Lunga School
Muoyo · education
K821,150 · Approved
Construction of 1x3 classroom block at Lwambi School
Mukukutu · education
K821,150 · Approved
Construction of 1x3 classroom block at Mwananyanda Primary School
Kambai · education
K831,150 · Approved
Construction of 1x3 classroom block at Sinungu School
Lyamakumba · education
K796,984 · Approved
Construction of a flushable toilet at Kaanda Primary School
Silowana · sanitation
K300,147 · Approved
Construction of a flushable toilet at Lyande Health Post
Shekela · sanitation
K300,147 · Approved
Construction of a flushable toilet at Makwibi Primary School
Muoyo · sanitation
K300,147 · Approved
Construction of a flushable toilet at Mande Community School
Muoyo · sanitation
K300,147 · Approved
Construction of a flushable toilet at Matongo Primary School
Nanjucha · sanitation
K300,147 · Approved
Construction of a flushable toilet at Nanjucha Primary School
Nanjucha · sanitation
K300,147 · Approved
Construction of a flushable toilet at Nyanye Community School
Shekela · sanitation
K300,274 · Approved
Construction of a flushable toilet at Shekela Primary School
Shekela · sanitation
K300,274 · Approved
Construction of a flushable toilet at Sinungu School
Lyamakumba · sanitation
K300,274 · Approved
Construction of a flushable toilet at Sipungu Primary School
Shekela · sanitation
K300,147 · Approved
Construction of a staff house at Nalolo Royal Health Clinic
Ukolo · health
K427,785 · Approved
Installation of solar powered water reticulation system at Kaanda Primary School
Silowana · water
K112,250 · Approved
Installation of solar powered water reticulation system at Lunga Combined School
Muoyo · water
K194,250 · Approved
Installation of solar powered water reticulation system at Lyande
Shekela · water
K192,250 · Approved
Installation of solar powered water reticulation system at Mande Community School
Muoyo · water
K194,250 · Approved
Installation of solar powered water reticulation system at Matongo Primary School
Nanjucha · water
K194,250 · Approved
Installation of solar powered water reticulation system at Nyanye Community School
Shekela · water
K194,250 · Approved
Installation of solar powered water reticulation system at Shekela Primary School
Shekela · water
K194,250 · Approved
Installation of solar powered water reticulation system at Sinungu Health Post
Lyamakumba · water
K194,250 · Approved
Installation of solar powered water reticulation system at Sinungu School
Lyamakumba · water
K192,250 · Approved
Installation of solar powered water reticulation system at Sipungu Primary School
Shekela · water
K194,250 · Approved
Phase 1 construction of a maternity wing at Litoya Rural Health Clinic
Lubosi · health
K450,000 · Approved
Procurement of 1,886 double desks
All Wards · education
K2,384,146 · Approved
Procurement of a police vehicle
All Wards · equipment
K1,000,000 · Approved
Procurement of an ambulance
All Wards · equipment
K1,000,000 · Approved
The audited record
The Auditor-General counted this constituency's projects in its audit of the CDF. These are the audit's own totals — a separate record from the council's published list above. The audit does not publish the projects name by name, so its totals are never added to the council list (some projects appear in both records). Figures are as printed in the Auditor-General's reports — where a report does not publish a figure, this page says so rather than estimating it.
Financial year 2024
| Component | Total funds available | Spent | Unspent | Unspent / spent |
|---|---|---|---|---|
| Community Projects | K16,177,003 | K16,217,210 | -K40,207 | 0% unspent · 100% spent |
| Empowerment Grant | K2,347,400 | K2,347,400 | K0 | 0% unspent · 100% spent |
| Secondary Boarding and Skills Development - Bursaries | K2,581,123 | K2,538,123 | K43,000 | 2% unspent · 98% spent |
| Loans | K3,718,794 | K3,619,000 | K99,794 | 3% unspent · 97% spent |
| Administrative Cost | K2,548,586 | K2,548,586 | K0 | 0% unspent · 100% spent |
Community Projects
balance brought forward K11,822,967 · 2024 funding K4,354,036
Empowerment Grant
balance brought forward K2,347,400 · 2024 funding K0
Secondary Boarding and Skills Development - Bursaries
balance brought forward K2,581,123 · 2024 funding K0
Loans
balance brought forward K6,178 · 2024 funding K3,445,664 · loan repayments received K212,354 · interest accrued K54,598
Administrative Cost
balance brought forward K1,016,804 · 2024 funding K1,531,782
Community Projects: balance brought forward K11,822,967 · 2024 funding K4,354,036
Empowerment Grant: balance brought forward K2,347,400 · 2024 funding K0
Secondary Boarding and Skills Development - Bursaries: balance brought forward K2,581,123 · 2024 funding K0
Loans: balance brought forward K6,178 · 2024 funding K3,445,664 · loan repayments received K212,354 · interest accrued K54,598
Administrative Cost: balance brought forward K1,016,804 · 2024 funding K1,531,782
2023 cohort — brought forward: 8 projects
2024 cohort — approved: 29 projects
Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2024 — Appendices 2.1–2.5 (money) and Appendix 3 (project status). Read the report (PDF)
Financial year 2023
| Component | Amount received | Spent | Unspent | Unspent / spent |
|---|---|---|---|---|
| Community Projects | K14,261,546 | K6,418,397 | K7,843,149 | 55% unspent · 45% spent |
| Empowerment Grants | K2,151,857 | K2,118,200 | K33,657 | 2% unspent · 98% spent |
| Soft Loans | Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table. | |||
| Secondary Boarding and Skills Development - Bursaries | K5,179,679 | K3,469,938 | K1,709,741 | 33% unspent · 67% spent |
| Administrative Costs | K1,415,695 | K1,415,695 | K0 | 0% unspent · 100% spent |
Community Projects
Empowerment Grants
Soft Loans
Not published by constituency in the FY2023 report — its Appendix 2.3 repeats the Empowerment Grants table instead of a loans table.
Secondary Boarding and Skills Development - Bursaries
Administrative Costs
2022 cohort — brought forward: 21 projects
2023 cohort — approved: 33 projects
Source: Report of the Auditor General on the Constituency Development Fund, financial year ended 31 December 2023 — Appendices 2.1–2.5 (money) and Appendices 3–4 (project status). Read the report (PDF)