Zambia CDF Tracker

Completion of a Health Post at Nsamba Rural Health Post

CDF project in Luapula, Luapula: Ongoing, budget K1,523,720. Source: Lunga Town Council.

Ongoing  Luapula, Luapula Province

StatusOngoing
BudgetK1,523,720
Funding yearNot published
WardNsalushi
Categoryhealth
ComponentCommunity
ContractorRichstone Engineering Limited
ConstituencyLuapula
ProvinceLuapula

A stalled project approved for completion under the 2025 CDF allocation (the council's 2025 approved list and the status table at minute PWDSSC/660 of its Q3 2025 minutes). Original allocation 2022; initial contract sum K1,523,720.09 (Kastenga General Dealers and Contractors); 2025 CDF top-up K380,930.02. The minutes report the contractor on site, working on finishes.

Source

Lunga Town Council — Minutes of the Ordinary Council Meeting, 21 October 2025 (Plans, Works Development and Social Services Committee status tables PWDSSC/658 and PWDSSC/660)