Completed Luapula, Luapula Province
StatusCompleted
BudgetK1,271,592
Funding yearNot published
WardNkutila
Categoryeducation
ComponentCommunity
ContractorJKMM General Dealers Limited
ConstituencyLuapula
ProvinceLuapula
A stalled project approved for completion under the 2025 CDF allocation (the council's 2025 approved list and the status table at minute PWDSSC/660 of its Q3 2025 minutes). Original allocation 2023; initial contract sum K1,271,592.44 (Owen Investments Limited); 2025 CDF top-up K117,898.11. The minutes record: 'Project completed and officially commissioned.'
Source
Lunga Town Council — Minutes of the Ordinary Council Meeting, 21 October 2025 (Plans, Works Development and Social Services Committee status tables PWDSSC/658 and PWDSSC/660)
View the published source