Water Borehole at Zimba Secondary School

CDF project in Mapatizya, Southern: Ongoing, budget K240,000. Source: Zimba Town Council.

Ongoing  Mapatizya, Southern Province

StatusOngoing
BudgetK240,000
Funding yearNot published
Ward—
Categorywater
ComponentCommunity
ContractorCashmo Construction Limited
ConstituencyMapatizya
ProvinceSouthern

The council reports K240,000 injected to drill a 200-metre industrial borehole at Zimba Secondary School, financed through the 5% disaster component of the CDF; its minutes of 15 May 2024 (PWD/624/05/24) record Cashmo Construction Limited contracted, mobilised, with works progressing well. Commissioning (August 2024) is reported by RCV (news) only and is not published. No CDF allocation year is stated.

Source

Zimba Town Council — Minutes of the Plans, Works, Development and Social Services Committee, 15 May 2024